NEW – REFORMER PILATES & SQUASH COURTS
Updated 9th September, 2026
Based on guest demand and a review of the current interest in our sports and fitness offering, it has been decided to develop a new Reformer Studio at Club La Santa.
The new studio will be created in the space currently occupied by Squash Courts 3 and 4, which will therefore close for renovation from 23 November
2026
NEW MAIN ENTRANCE, SUPERMARKET AND RENOVATION OF TOWERS
Updated 12th August, 2026
From 12th April 2026 until early February 2028, Club La Santa will undergo exciting construction of a new administration building at the stadium gate. This new building will become the main entrance to Club La Santa and will house key departments, including:
Reception, Sports Booking, Groups and Conferences, Reservations, Administration, IT, Marketing, Events, and Sports.
As part of these improvements, a new supermarket will also be built, and five towers in the original part of Club La Santa –Towers 1, 3, 50, 51, and 52– will be renovated and upgraded to Comfort apartments. This includes full refurbishment of staircases and apartments.
Renovation timeline
- 12th April – 14th December, 2026: Tower-by-tower refurbishment of all apartments in Towers 1, 3, 50, 51 and 52 until 30th August.
- 4th January 2027 – February 2028: Demolition of the Timeshare office at the stadium gate, followed by construction of the new building and supermarket.
These upgrades are designed to enhance the overall experience at Club La Santa and create a more cohesive and welcoming environment. While construction may cause occasional noise in affected areas, we assure you we will do our best to minimize any inconvenience.
You can follow updates and progress here on our website.
Timeshare owners affected by the renovation will be contacted closer to their arrival date.
We look forward to building the future of Club La Santa!
We are excited to share these visual representations of what the areas will look like once renovations have been completed!
NEW MOTOR SKILLS HALL AND CLIMBING WALL IN THE NORTH HALL
Updated 11th August, 2026
From mid-October 2026 to 1 May 2027, the North Hall will undergo an exciting transformation. The new hall will offer:
- A sports hall with four badminton courts, facilities for volleyball, 3v3 floorball, and climbing.
- A new motor skills hall for children aged six years and up.
Phase 1: Mid-October 2026 to mid-February 2027
A dividing wall will be built to separate the two halls, along with the climbing wall. During this time, badminton, handball and other activities normally held in the North Hall will move to the South Hall.
Phase 2: Mid-February 2027 to 1 May 2027
Construction of the new motor skills hall. During this phase, badminton will be available in one half of the North Hall as well as in the South Hall.
NEW PLAYGROUND
Updated 11th August, 2026
From February to May 2027, the playground next to the Pool Bar will be upgraded. During the construction, the playground by the children’s pool, the trampoline area, and the outdoor Play Time area remain available and a variety of children’s toys and games will be offered via Sports Booking.
Once complete, the new Pool Bar area will feature a brand-new playground for our younger guests.
RENOVATION OF THE POOL BAR AND GREEN BAR
Updated 11th August, 2026
The Pool Bar and Green Bar are expected to reopen on 1 April 2027. While the final phase will take longer than planned, our priority remains delivering a lasting improvement to the resort experience, done to the highest standard.
This project will enhance the area’s relaxing atmosphere, ideal for socialising, while modernising and improving the facilities of this iconic part of Club La Santa. The new Pool Bar will feature a larger kitchen, more space, and a sustainable design, as we’re replacing all gas equipment with electric, a step towards making Club La Santa an even greener and more energy-efficient resort. And much more to be further announced!
During this period:
- Both bars will be closed.
- Construction noise may be noticeable in the surrounding area, with work taking place from Monday to Saturday from 08:00 to 18:00.
- The children’s playground is partly open but may be closed at times during the renovation. Additional children’s activities are available in the children’s pool area.
- The Dive Centre will temporarily close from 31 August 2026 for approximately four months. We’re exploring alternative snorkelling experiences for guests during this period and will share further details as soon as they are confirmed. Diving will continue to offer snorkelling safaris from 31 August throughout the four-month closure of the Dive Centre. Their temporary office will be located in a tent next to the Wellness Centre, by the Leisure Pool from this Saturday 29/08.
Snorkelling safaris can be booked at their temporary office or via their usual contact details, during their regular opening hours.
Diving classes will not be available during the four-month closure.
These drawings are preliminary and subject to change:
TEMPORARY POOL BAR
While the renovation is underway, a temporary Pool Bar and lounge area will be set up next to The Lawn and Restaurant Atlántico. Guests can enjoy an all-day menu and refreshments here, with great views of the leisure pool and the Atlantic Ocean. All other restaurants will remain open and ready to welcome you throughout your stay at Club La Santa.